See Ethernet Ports.
See Server Management Connection Options.
Choose one of the following options:
After initial configuration, you can connect and configure access using the Ethernet management (NET MGT) port.
Use Velcro straps to secure power cords to the power supply handles.
The server is equipped with two power supplies. The server can operate with one power source; however, using only one power source eliminates redundancy.
Oracle Server X8-2:
Oracle Server X8-2L
![]() | Caution - Damage to Server Components: Do not operate the server unless all included fans and components are fully installed. |
When the server power cords are connected, the following actions occur:
The green AC OK power supply indicators (LEDs) light.
The Oracle ILOM SP initializes. During initialization, the green SP OK LED flashes rapidly.
Once the Oracle ILOM SP has fully initialized, the green SP OK LED is steady on and the green System OK LED flashes slowly, indicating that the host is in Standby power mode.
In Standby power mode, the server is not initialized or powered on.