Completing the Planning Subtab
Use the following steps to complete the Planning subtab.
To complete the planning subtab:
-
Click the Planning subtab.
-
In the Rates section, enter a Std Rate (Min/Unit) that matches the NetSuite routing record run rate.
NetSuite populates the Std Rate (Unit/Hr) field when the manufacturing work bench record saves.
-
Enter a Unit of Measure.
-
In the Lead Time and Off Sets section, enter a Setup Time (Min) that matches the NetSuite routing record setup time in minutes.
-
To determine how to schedule this operation to lag behind its predecessor, select a Lag Type from the list.
-
In the Lag Value field, enter either the number of minutes or units to quantify the lag offset.
Units should correspond to the selected lag type.
-
In the Hold Time (Min) field, enter the number of minutes that the asset should remain unavailable following a production run.
-
In the Batching section, in the Batch Minimum field, enter the smallest batch value that can be produced.
-
In the Batch Maximum field, enter the largest batch value that can be produced.
Note:Batch minimum and maximum values must be greater than zero and in the same units as the assembly stock unit of measure.
-
In the Incremental Qty field, enter the incremental batch size to step from a minimum batch to a maximum batch.
Use this value to determine the last batch size needed to fulfill a work order quantity.
-
If multiple batches can be processed at the same time, enter the number of Concurrent Assets (Split Order) allowed to run on a single work order.
The value must not exceed the total number of assets associated with the work center or this workbench record, whichever is less.
Note:Do not use the Concurrent Assets (Split Order) field independently. You should use the field in conjunction with other batch fields.
-
Click Save.