Prepare the Rack
Verify the rack meets requirements to ensure a smooth library installation.
Rack Requirements
-
Rack must contain four posts.
-
Front and rear service clearance must be at least 965 mm (38 inches).
-
Front of the rack must face the cool aisle and the rear face the warm aisle.
-
Rack must be level (left to right and front to back). The installed library must remain level for proper operation.
-
Vertical rail spacing should be between 457 mm (18 in) and 902 mm (35.5 in.
-
Provide sufficient rack space to install the Base Module (3U) and any Expansion Modules (2U each).
Rack Preparation
-
Position the power distribution unit (PDU) on the right side of the rack as viewed from the rear of the rack (see Figure 2-1). The power supply outlets are on the right side of the SL150 library. Refer to the rack and power distribution unit documentation for instructions to install the PDU
-
To provide access during installation of a library module, remove the front door from the rack.
Figure 2-1 Rear View of Sun Rack II (PDU on Right Side)

Illustration Legend:
1 - Power Distribution Unit (PDU)