Criteria for the Overall Status of a Project

The system determines the overall status of a project by considering the importance of project KPIs and a project's KPI value. Each KPI has an assigned relative importance while each KPI value has a corresponding KPI score.

The overall status criteria use the following KPIs:

Depending on a project's KPI value, it can be classified as High, Medium, or Low. The total score for all project KPIs determines the overall status of a project.

The following table shows how the overall status is determined for a project:

Project

Budget vs. EAC

Tasks Overdue

Tasks Not Resourced

Charges Not Invoiced

Overall Status

Project A

High

Low

Low

Low

High

Project B

Low

Medium

Low

Medium

Medium

Project C

Low

Low

Medium

Low

Low