Facility Power Checklist
This section provides a server facility power checklist.
Complete the following checklist to ensure that the facility power requirements are met for the data center in which the server will be installed.
| Facility Power Considerations | Yes | No | N/A | Comment |
|---|---|---|---|---|
|
Do you know the required operating voltage and electric current level of the device and peripherals? |
||||
|
Are enough power outlets provided within 2 meters (6.5 feet) for each rack? |
||||
|
Do the power outlets have appropriate socket receptacles? |
||||
|
Will optional ground cables be attached to the rack? |
||||
|
Are the circuit breakers for the equipment suitable in terms of voltage and current-carrying capacities? |
||||
|
Does the power frequency meet the equipment specifications? |
||||
|
Will system power be delivered from two separate grids? |
||||
|
Is there a UPS to power the equipment? |
||||
|
Do you have the minimum required power sources to support the power load for the new hardware? Use kilowatt (kW)/kilovolt (kVA) to express power load. |