Monitoring the Supply Plan Status

After you submit the supply plan generation page, some plans may take time to be generated. You can check the status of plan generation to monitor progress.

Important:

Did you know that the NetSuite Supply Planning (MRP) solution replaces Time-Phased Planning, with more features and better performance?

New customers should use the new Supply Planning (MRP) solution. Existing customers should develop a plan to move from Time-Phased Planning to the new solution.

To monitor supply plan creation status:

  1. Go to Transactions > Demand Planning > Generate Item Supply Plan > Status.

  2. The Generate Item Supply Plan Status page shows a list of page submissions.

  3. For each line, the following shows:

    • Date and time created

    • Percent complete

    • Status

  4. You can filter the list of plans by entering a date range in the From and To fields.

  5. After all supply plan calculations complete, the status for the line shows as Complete