Setting a Project Baseline

After you’ve finalized the details of your project, you can set a project baseline. This baseline is a snapshot of your original estimates before any work starts, so you can compare it to actual work and any schedule changes as the project moves forward.

Note:

Only users with Edit or Full permission for Projects can set a project baseline.

To set a project baseline:

  1. Go to Lists > Relationships > Projects and click View next to the project for which you want to set a baseline.

  2. On the project record, click Set Baseline.

Now, the baseline data is recorded. The project record now shows a Last Baseline Date field in the header that displays the date you most recently set a baseline.

If you need to reset the baseline data for a project, you can click Set Baseline again. The data previously stored in the baseline fields will be overwritten with the latest data.