Completing the Shop Calendar Subtab
Use the following steps to complete the Shop Calendar subtab.
To complete the shop calendar subtab:
-
Click the Shop Calendar subtab.
-
Enter a Start Time with the HH:MM am/pm format.
This is the time the work day begins.
-
Enter an End Time with the HH:MM am/pm format.
This is the time the work day finishes.
-
Enter the total operating Hours.
For example, if a Monday shift starts at 09:00 and ends at 16:30, Monday’s operating hours are 7.5.
-
For days that your shop does not operate, enter 0.
-
Deduct break times from the total unless the work center continues to run during the break.
-
Ensure to schedule half days, off days, or work stoppages.
-
-
Repeat steps 2–4 for each day the work center operates.
-
Click Save.
Related Topics
- Creating an Advanced Manufacturing Work Center
- Editing an Advanced Manufacturing Work Center
- Completing the Assets Subtab
- Completing the RCP Parameters Subtab
- Creating an Advanced Manufacturing Location
- Creating Manufacturing Work Benches
- Conventional Work Order Plug-ins
- Configuring Assemblies and Routings