Overriding Actual Production Dates

The following procedure describes how to manually change actual production dates.

To override a actual production date:

  1. On the work order, below the Actual Production Start or End Date, click Enter Manually.

  2. Select a new date from the calendar.

    For example, you can change the date from Dec. 2 to Dec. 3.

  3. Click Save.

Related Topics