Project Schedule Calculation in the Project Center
The project schedule is recalculated automatically after:
-
You modify the Start date or Finish date for a task.
-
You drag a task into a phase and the task modifies the Start date or Finish date for the phase.
-
You add or modify one or more predecessors to a task or phase.
-
You add or modify Planned hours, if the project schedule calculation is based on assignments (default).
-
You add or modify hours in the booking grid and click Save, if the project schedule calculation is based on bookings. For more information about calculating the project schedule based on bookings instead of assignments, see Basing Project Schedule Calculation on Bookings for a Project.
When you go to the project center or reload the project center page, SuiteProjects Pro checks if any changes impacting the project schedule were made outside of the project center and triggers the project schedule calculation if needed.
All calculated Start dates and Finish dates in the project sequence are updated. Planned hours are also updated if the project schedule calculation is based on bookings.
You can set individual projects to calculate the following information based on bookings instead of assignments:
-
Calculated task, phase and project Start dates and Finish dates.
-
Planned hours.
-
% Complete.
For more information , see Basing Project Schedule Calculation on Bookings for a Project.
When the calculation is in progress, information in the Start, Finish and Planned hours columns cannot be edited and loading spinners are visible in the column headers.