Project Schedule Calculation in the Project Center

The project schedule is recalculated automatically after:

When you go to the project center or reload the project center page, SuiteProjects Pro checks if any changes impacting the project schedule were made outside of the project center and triggers the project schedule calculation if needed.

All calculated Start dates and Finish dates in the project sequence are updated. Planned hours are also updated if the project schedule calculation is based on bookings.

Note:

You can set individual projects to calculate the following information based on bookings instead of assignments:

  • Calculated task, phase and project Start dates and Finish dates.

  • Planned hours.

  • % Complete.

For more information , see Basing Project Schedule Calculation on Bookings for a Project.

When the calculation is in progress, information in the Start, Finish and Planned hours columns cannot be edited and loading spinners are visible in the column headers.