Project Recalculation Optimization

SuiteProjects Pro has several features which let you optimize project recalculation when adding or modifying tasks to projects. The optimization improves loading time for the following views after creating, duplicating, deleting, or modifying a task associated with the project you are viewing, or after moving or copying a task to another project.

By default, SuiteProjects Pro recalculates the project plan and reloads the view every time the user makes a change to the task, phase or milestone. The following features change this default behavior to optimize project recalculation. You can use any of these features in combination or independently.

Enabling Employees to Run the Project Recalculation Manually

This feature can be enabled for any project on the project properties form. After you enable the features, employees can add tasks, delete tasks, modify the planned hours for any number of tasks, create repeat tasks or split tasks without having to wait for the project recalculation to complete between each change. Employees can then run the project recalculation manually.

  • On the Phases/Tasks > List, Phases/Tasks > Worksheet or Phases/Tasks > Task Assignments views, a link is available at the top of the view. Click the link to recalculate the project.

  • On the Phases/Tasks > Outline or Phases/Tasks > Gantt, a warning message appears when you go to the view. Click the link in the warning message to recalculate the project.

To enable employees to run the project recalculation manually

  1. Go to Projects > Projects > [Select a project] > Properties.

  2. Under the General form section, check the Allow the employee to initiate the project recalculation box.

    Note:

    If you cannot see the Allow the user to initiate project recalculation box on the project properties page, check the form permissions, or contact your account administrator.

  3. Click Save

Phase and tasks list and Project Outline view showing the manual recalculation link.