Create and Manage Sprints

You can create and manage sprints from the Backlog view of a Scrum board. You must be a project owner or the board owner to create, edit, update, or delete a sprint.

When an issue is assigned to a sprint, the sprint is displayed in all boards whose issue query returns any issue of the sprint in its result. You might find such sprints in your board. Note that you can’t edit or start sprints that you didn’t create, or sprints that weren’t created in the current board.

If there are no issues assigned to a sprint, the sprint is available only in the board in which it was created.

Action How To

Create a sprint

  1. From the toggle buttons, click Backlog.
  2. In the Backlog view, click + Add Sprint.

  3. In the Add Sprint dialog box, enter the sprint name. If the Scrum board uses story points, then specify the sprint’s capacity.

  4. Click OK.

Edit a sprint

  1. From the toggle buttons, click Backlog.
  2. In the Backlog view, for an inactive sprint, click ... and select Edit sprint.

    If the sprint is active (or started), click Edit Sprint.

  3. In the Edit Sprint dialog box, you can update the sprint’s name, board, start and end dates, and its capacity in story points.

    The Story Points field is available if story points were selected as the estimation for the board.

  4. Click OK.

Start a sprint

When you or your team begin work on a sprint and want to update the issues of the sprint, you must first start (or activate) it.

  1. From the toggle buttons, click Backlog.
  2. In the Backlog view, for the sprint that you want to start, click Start Sprint.

  3. In the Start Sprint dialog box, specify the start and end dates of the sprint.

    If necessary, update the sprint’s name and its estimate.

  4. Click Start.

The started sprint is now available in the Active Sprints view.

Reorder a sprint

In the Backlog view, by default, the inactive sprints (also called as future sprints) in the order they were created. You can change their display order manually.

For the inactive sprint that you want to move up or down, click ... and select Move sprint up or Move sprint down.

You cannot change the order of active sprints. The active sprints are ordered by Start Date in the Backlog view. If two sprints have the same Start Date, then they are ordered by name.

Move a sprint to another board

  1. From the toggle buttons, click Backlog.
  2. In the Backlog view, for an inactive sprint, click ... and select Edit sprint.

    If the sprint is active (or started), click Edit Sprint.

  3. In the Edit Sprint dialog box, from the Board drop-down list, select the target board.

  4. Click OK.

Delete a sprint

You can delete an inactive sprint from the Backlog view of the board. You can’t delete an active sprint.

For the inactive sprint that you want to delete, click the ... and select Delete Sprint. The sprint is deleted and all issues of the sprint are moved to the Backlog list.