Prerequisite Setup
Forecasts and sales orders were entered for nine time periods. Verify that the MRP Time Periods processing option in the MPS Regeneration program (R3482) is set to 9 periods and the Periods in MRP Window field in the Kanban Size Calculation Parameter Definition program (P3018) is set to 9.
The MRP Regeneration program ran for five days, three weeks, and one month. The resulting time series is:
Date |
FSCU Quantity |
SOU Quantity |
Sum of Included Demands |
---|---|---|---|
February 2 |
100 |
30 |
130 |
February 3 |
200 |
40 |
240 |
February 4 |
300 |
50 |
350 |
February 5 |
300 |
50 |
350 |
February 6 |
200 |
100 |
300 |
February 13 |
200 |
100 |
300 |
February 20 |
300 |
200 |
500 |
February 27 |
250 |
200 |
450 |
March 31 |
100 |
200 |
300 |
The calculation method has been set up using the Kanban Size Calculation Definition program (P3017). The calculation method has calculation-specific parameter values, as defined in the Kanban Size Calculation Parameter Definition program:
Parameter |
Parameter Value |
---|---|
Periods in MRP window |
9 |
Days built per week |
5 |
Days built per month |
20 |
Scan delta days |
1 |
Lead time delivery (days) |
2 |
Vendor split percent |
0 |
Safety stock |
50 |
Demand split percent |
100 |
Container size |
50 |
Minimum kanban size |
20 |
Maximum kanban size |
60 |