Retainage Calculations

This equation shows how the system calculated the percent complete:

(Net Amount) ÷ (Schedule of Values) = (Percent Complete)

7,200.00 ÷ 17,000.00 = 0.423529411

This equation shows how the system calculated the total retainage:

(Schedule of Values) × (Retainage Completion) × (Retainage Percentage) = (Retainage Amount)

17,000.00 × 0.30 × 0.10 = 510.00

This table shows how the system calculated the retainage for each billing line:

Billing Line

(Net Amount) ÷ (Total Net Amount) × (Retainage Amount) = (Billing Line Retainage Amount)

001

1,200.00 ÷ 7,200.00 × 510.00 = 85.00

002

6,000.00 ÷ 7,200.00 × 510.00 = 425.00