Retainage Calculations

This equation shows how the system calculated the percent complete:

(Net Amount) ÷ (Schedule of Values) = (Percent Complete)

7,200.00 ÷ 12,000.00= 0.6

This equation shows how the system calculated the total retainage:

(Schedule of Values) × (Retainage Completion) × (Retainage Percentage) = (Retainage Amount)

12,000.00 × 0.30 × 0.10 = 360.00

This table shows how the system calculated the retainage for each billing line:

Billing Line

(Net Amount) ÷ (Total Net Amount) × (Retainage Amount) = Billing Line Retainage Amount

001

1,200.00 ÷ 7,200.00 × 360.00 = 60.00

002

6,000.00 ÷ 7,200.00 × 360.00 = 300.00