Setting Up a Column Definition for Non-JU Budget Unit Ledgers
To set up a column definition for non-JU budget unit ledgers:
- Access the Project Status Inquiry Column Definitions form. - Form Name - Form ID - Navigation - Project Status Inquiry Column Definitions - W51X90B - Project Status Inquiry (G51411). - Column Definitions (P51X90). - Click Add on the Work with Project Status Inquiry Column Definitions form.   
- Enter values in these fields and select or clear the options: - Column Name
- Enter a name for the column that you create. This field is required. 
- Description
- Enter a description for the column that you create. This field is required. 
- Column Heading
- Enter the name that you want to use for a label for the column when the column name appears in the Work with Project Status Inquiry and Project Status Inquiry forms. This field is required. 
- Column Type
- Select Non-JA Budget Unit Ledgers. 
- Budget Flag
- Select an option to specify whether to include original or revised budgets. - Values are: - Original Budget - Revised Budget 
- Totaling Method
- Select an option to specify whether the system sums or averages the values in the column, or whether the system does not apply any totaling method. See Understanding Totaling Methods. - Values are: - Average - Exclude zero amounts. The system does not include zero amounts when it averages the values in the column. - Average - Include zero amounts. The system includes zero amounts when it averages the values in the column. - None. The system does not apply a totaling method to the column values. - Sum. The system adds the values in the column. This is the default value. 
- Display Decimal Override
- Enter the number of decimal places to override the default decimal value for the currency amount, unit, or unit price of the column. See Understanding Decimal Display Values. 
- Scaling Multiplier
- Enter the factor by which the system multiplies amounts or units in a column. The system multiplies the accumulated amounts by the multiplier factor before it displays the result on the Project Status Inquiry form. - For example, if you want to scale large numbers to thousands, enter.001. If you want percentages to appear as whole numbers, enter 100. 
- Units Flag
- The system selects this check box because the column type is for units. 
- Header Units Flag
- Select the Header Units Flag check box to use header units instead of account units. 
 
- Click OK.