The data center must meet the following electrical requirements for installation of a Sun Blade 6000 system:
Four 200–240 VAC, 16A/20A branch circuits, one for each of the AC inlets on the system, are required.
Each AC inlet requires a separate power cord; therefore, four power cords are required. The power cord must be rated at 16A or 20A, depending on the site location.
If you are using an Oracle MPS in the cabinet, refer to the documentation supplied with the cabinet for the MPS power requirements.
If you are not using an MPS, you must supply a branch circuit with a connector that meets the requirements of your system.