B.7 Safety Checklist

Complete the following checklist to ensure that the safety requirements are met. For information about safety, see Operational Procedures for Exalogic Machines, and Temperature and Humidity Requirements.

Safety Checklist Considerations Yes No N/A Comment

Is there an emergency power shut off?

       

Is there a fire protection system in the data center room?

       

Is the computer room adequately equipped to extinguish a fire?

       

Is antistatic flooring installed?

       

Is the floor below the raised floor free of obstacles and blockages?

       